SOP for Preventive Maintenance of Lifter EN-71

A Standard Operating Procedure of the Preventive Maintenance of Lifter (such as a forklift or any other lifting equipment) outlines the step-by-step instructions for conducting routine maintenance tasks to ensure the safe and optimal functioning of the lifter. Here’s a sample SOP.Preventive Maintenance of Lifter

SOP for Preventive Maintenance of Lifter

  • OBJECTIVE:
    • To lay down the Procedure for Preventive Maintenance of Lifter in plant.
  • SCOPE:
    • This SOP is applicable to preventive maintenance of Lifter in plant .
  • RESPONSIBILITY:
    • Technician/ Operator shall be responsible for proper execution of preventive maintenance as per SOP of Preventive Maintenance of Lifter
    • Engineering – Head shall be responsible for reviewing the SOP and for ensuring proper execution of Preventive Maintenance of Lifter
  • ACCOUNTABILITY:
    • Engineering – Head shall be accountable for proper implementation of the SOP.
  • DEFINITIONS:
    • Nil
  • PROCEDURE:
    • Preventive maintenance shall be executed as per the SOP No.: SOP/EN/XXXYYY- Execution of Preventive Maintenance.
    • Ensure that the spare parts are available at the time of preventive maintenance.
  • Preventive Maintenance – Mechanical
  • Switch off the Power supply of Machine. Place “Under Preventive Maintenance” board on the machine.
    • Check the oil level of Hydraulic Power Pack and top up if required.
    • Check the oil condition, change if required with oil grade 68/Equivalent.
    • Check the oil leakage from machine, If found rectify the same.
    • Check the machine for unusual noise and vibration.
    • Clean the oil filter.
    • Check the motors for any abnormalities.
    • Check all push buttons for damages and proper function.
    • Remove “Under Preventive maintenance” board after completion of preventive maintenance.
    • Record the observation on Preventive Maintenance checklist of Lifter.
    • Checking shall be done on quarterly basis ±7 days.
  • Preventive Maintenance – Electrical
  • Checking of Terminals, Wiring and Components
    • Ensure that the power supply to the machine is switched off.
    • Check and ensure by using appropriate tools that all the wires are properly tightened.
    • Check the over load relay for proper functioning. This is checked by lowering its setting, if the overloads relay trips its contactor the overload relay is functioning.
    • Checking shall be done on quarterly basis ±7days.
  • Post Preventive Maintenance – Check List
    • Whenever any modifications and major works are carried out to the equipment, the same shall be mentioned in the equipment history card as per the respective SOP.
    • Ensure that the equipment is running smoothly, without any abnormality.
    • If any abnormality is observed in the above, same will be attended in co-ordination with User department Head.
    • Record  the preventive maintenance activity as per  the  format  No  : SOP/EN/XXXYYY Preventive   maintenance   check  list  & record.
  • ABBREVIATIONS
    • CRF No.   :     Change Request Form number
    • QA            :     Quality Assurance
    • PM            :     Preventive Maintenance
    • EN            :    Engineering
  • REFERENCES
    • Nil.  
  • DISTRIBUTION LIST
    • SOP shall be distributed to following departments Quality Assurance, Engineering as per user request.
  • ANNEXURES
    • Preventive Maintenance Checklist & record for Lifter :    SOP/EN/XXXYYY

Checklist and Records of Preventive Maintenance of Lifter:

CHECKLIST & RECORD FOR LIFTER

Equipment Name   Location  
Equipment ID   Frequency  
Things to be done: Check List Remarks
Quarterly Check List    
1. Check the oil level of Hydraulic Power Pack and top up if required.    
2.  Check the oil condition.    
3.  Check the motors for any abnormalities.    
4.  Check the machine for unusual noise and vibration.    
5.  Clean the oil filter.    
6.  Check the over load relay for proper functioning. This is checked by  lowering its setting, if the overloads relay trips its contactor the overload relay is functioning    